Friday, August 1, 2008
Lockup 1 continued....
Lockup 1 almost complete along with many lockup 2 items completed already. Will only be a couple of weeks before lockup 2 is finished. Here's some more pics.






Friday, July 18, 2008
Lockup 1
Latest progress... Brick layers have been onsite. Lower level brick work started.
Progress from last week/early this week. Roof tiling to lower level is pretty much done, foil, electrical and plumbing started.
Well we've been in New Zealand for 10 days and not much had happened while we were away. Got back on the 11th July, yet no progress until this week. Power company did however finish off the electricity pit, and we're powered up now!
Progress this week - Roof tiles, level 1 Facia's and spouting. To come is more brick work and level 1 eave lining. Here's some pics.
Monday, June 16, 2008
Frame Stage 2
Well that's it for frame stage 1. All went smoothly so far, frame inspection completed last week and no problems. Have to pay up this week.
Noticed on Friday (the 13th) that all the aluminum windows have been delivered to the site. Went past today (16th) after work and found that most had been installed. Was a bit dark to get any decent photo's, so Jo will get some decent pics tomorrow hopefully.
here's the pics from 17th June 2008;







Noticed on Friday (the 13th) that all the aluminum windows have been delivered to the site. Went past today (16th) after work and found that most had been installed. Was a bit dark to get any decent photo's, so Jo will get some decent pics tomorrow hopefully.
here's the pics from 17th June 2008;
Wednesday, May 28, 2008
Upstairs Frame
Only a couple of days after lower level frame was completed, the upstairs frame is up. (update: above pics now roof is going on!)
Saturday, May 24, 2008
Frame Stage 1
Well the power is still out, but the guys are bringing in generators of some sort to keep the job going. This week saw the frame arrive with the ground floor up. Next week I suspect the upper story to be up with roof trusses. Then I cough up more $$$.
Friday, May 16, 2008
Surprise, Surprise
Well we had a nice surprise today arrive in the mail. It was a progress letter from Darnley, our builders. We expected that no progress would be made as we're still waiting for power, but to our surprise, it actually said that they had begun the brick work to the garage.
Spoke to the supervisor during the day, and he just didn't want the project falling back that far, so he organised a petrol generator to get the guys working. No cost to us!
So here's where there at so far. Working towards Frame stage 1.
Spoke to the supervisor during the day, and he just didn't want the project falling back that far, so he organised a petrol generator to get the guys working. No cost to us!
So here's where there at so far. Working towards Frame stage 1.
Wednesday, May 7, 2008
First Hurdle
Well we got to base stage with no problem. Next step is for brick work and lower frame etc. This is where the hurdle appears. This stage requires the site to be powered. Electricians put in the application to the power company for connection. Power company then advises that they are not able to connect us into the existing electrical pit on the street, and will need to make a new pit, basically specifically for us.
Could take up to 6 weeks. Our builders did offer an alternative which was at our expense though, and that's to hire a generator which could cost up to $500pw. I said thanks, but no thanks, i'll just wait!
Until next time!
Could take up to 6 weeks. Our builders did offer an alternative which was at our expense though, and that's to hire a generator which could cost up to $500pw. I said thanks, but no thanks, i'll just wait!
Until next time!