Latest progress... Brick layers have been onsite. Lower level brick work started.
Progress from last week/early this week. Roof tiling to lower level is pretty much done, foil, electrical and plumbing started.
Well we've been in New Zealand for 10 days and not much had happened while we were away. Got back on the 11th July, yet no progress until this week. Power company did however finish off the electricity pit, and we're powered up now!
Progress this week - Roof tiles, level 1 Facia's and spouting. To come is more brick work and level 1 eave lining. Here's some pics.