Thursday, August 28, 2008

Render finished

Since the last update the rendering was completed. We are very happy with the way it's turned out. Other items that have been done; square set cornices, 140mm skirting boards to gnd, 90mm upstairs, architraves, exterior painting of eves, stair case installed and electrical cutout. Here's some pictures of the rendered finish. Feature tiles to entry still to come.




Thursday, August 14, 2008

Render - Getting there

Here's some pics from today. The renderer's have completed the 2nd coat to the lower level (and some parts of upstairs), with the 3rd coat (color) to come soon. Upstairs rendering should be finished next week sometime, with color to follow a week or so later.






The face brick work here will be finished in a black/orange metallic 600x600 tile.

Wednesday, August 13, 2008

Lockup Stage 2 - Plaster

From downstairs bedroom looking at entry door.



Picture taken from kitchen/meals/family area, looking up into hall to front of house.



Looking out from formal dining/living room.



Looking down the hall from entry area.



Looking into the downstairs bedroom from main entry.



Downstairs bedroom sidelight.



Media room highlight window.



Back of the media room.



Looking towards the kitchen/meals area.



Looking towards the family room.



Kitchen area...

Monday, August 4, 2008

Lockup 1 & 2 almost complete

Well lockup 1 & 2 will be completed this week.

We've got the ducted vac roughed in today, along with video door phone's, split system A/C sytems, insulation going in over the next couple of days, then plastering will start on Wed/Thurs. The renderers have started and will be finished by next week. Undercoat in progress below, then final 2 coats to come.

Here's a few pics from today.




Friday, August 1, 2008

Lockup 1 continued....

Lockup 1 almost complete along with many lockup 2 items completed already. Will only be a couple of weeks before lockup 2 is finished. Here's some more pics.